Introduction
Busselton Jetty
Permacast was selected by the head contractor, Shorewater Marine, to manufacture 84 precast concrete panels to replace the existing deteriorating panels on the Busselton Jetty. To meet stringent specifications, these panels were produced in a highly controlled precast factory environment. This included achieving a consistent anti-slip concrete finish and additional reinforcement cover to ensure safety and durability in a marine environment. Due to the panels’ delicate geometry and shallow depth, lifting and transportation were completed carefully to prevent damage and maintain its structural integrity.
Project Overview
Permacast contributed to the refurbishment of Busselton Jetty by replacing 84 deteriorating concrete panels with new precast units, expertly manufactured to meet strict specifications.
Client
Shorewater Marine
Location
Busselton
Duration
2025
Industry
Marine
Project Specifications
- 84 precast concrete panels, each measuring 4000x740x130mm
Project Details
- Expertly engineered panels meeting precise specifications to ensure durability in a marine setting
- Achieved anti-slip concrete finish for all panels
- Managed careful, just-in-time delivery of delicate panels to prevent damage
Introduction
Esperance Jetty
Replacing the historic Tanker Jetty, Permacast manufactured and delivered the precast elements for the new, award-winning Esperance Jetty. The scope of work included 129 deck planks, produced using Caltite marine concrete to meet the durability and performance standards for a harsh coastal setting. It also required the careful execution of transport logistics to Esperance, ensuring safe handling and on-time delivery to meet project deadlines.
Project Overview
Permacast manufactured the precast concrete elements for the Esperance Jetty, expertly engineered to withstand a harsh marine environment.
Client
Maritime Construction
Location
Esperance
Duration
2021
Industry
Marine
Project Specifications
- 129 Deck Planks, weighing 14 tonnes each
Project Details
- Utilised Caltite marine concrete to ensure waterproofing and long-term durability in a marine environment.
- Planned and executed long-distance transport logistics to Esperance.